Practical field guide
Payroll teams run parallel pays properly: how many to run, what to compare, how to investigate variances, tolerances and sign-off.
The short answer#
A payroll parallel run processes the same pay period in the old and new systems and compares the results. Run at least two per pay frequency and entity, include periods with public holidays, terminations, back pay and leave loading, and keep going until every variance is explained. Compare totals (gross, tax, super, deductions, net, employer costs), every employee's result, and outputs: payslips, bank file, super file, STP payload (including QE and super liability) and GL journal. Classify each variance as new system wrong, old system wrong, data difference, expected design change, or unexplained. Set tolerances before you start, accept zero unexplained variances at employee level, and get sign-off from payroll, finance, HR and the steering committee.
Why parallel runs matter#
A parallel run means running the same pay period through your old and new payroll systems, then comparing the results. It's the single most important test in a payroll implementation. It's also the one most often cut short when the go-live date looks at risk.
Don't cut it short. The cost of an extra parallel run is a few days. The cost of a bad first live pay is trust, back pay and sometimes a remediation program.
How many?#
There's no magic number, but here's a sensible guide:
- At least two full parallel runs for every pay frequency and entity.
- Include a period with unusual events: public holidays, leave loading, end of month, a backpay, terminations.
- Keep running until variances are explained. The goal isn't a number of runs. It's a run where every variance has a known cause.
If you have several awards with complex rules, plan for more.
What to compare#
Compare at three levels:
1. Totals
- Gross pay, by entity and pay frequency
- Tax withheld
- Super
- Deductions
- Net pay
- Employer costs (payroll tax base, workers comp base)
2. Employee level
- Gross, tax, super, net for every employee
- Hours by type (ordinary, overtime, penalties)
- Leave accrued and taken
- Allowances
3. Outputs
- Payslips (format and content)
- Bank file
- Super file and contribution amounts
- STP payload, including QE and super liability
- General ledger journal
Many teams compare net pay and stop. Compare the STP payload and the GL journal too. Errors there don't show up until later, and they're painful to fix.
Investigating variances#
For every variance, find the cause and classify it:
| Classification | Meaning | Action |
|---|---|---|
| New system wrong | Configuration error | Fix and re-test |
| Old system wrong | Historical error found | Confirm with payroll lead; consider remediation for past periods |
| Data difference | Different input data in each system | Fix data or timing; re-test |
| Expected difference | Design change agreed in discovery (like rounding) | Document; no action |
| Unexplained | Cause unknown | Investigate. Can't sign off with unexplained variances |
"Old system wrong" is more common than people expect. Parallel runs often reveal historical underpayments. Have a plan for what you'll do if you find one, including legal advice. See our wage underpayment guide.
Tolerance#
Set tolerances before you start, and agree them with finance:
- Totals: variance within a small, agreed amount per run (often cents, from rounding)
- Employee level: zero unexplained variances. Explained variances documented.
Don't accept "it's within a few dollars" for an individual employee without knowing why. A few dollars every pay over years is an underpayment.
Who signs off#
- Payroll lead: every variance explained and resolved
- Finance: totals, GL and costs reconcile
- HR: leave and entitlements correct
- Project steering committee: readiness to go live
Common mistakes#
- Running parallels on a quiet period with no complexity.
- Comparing only net pay.
- Different input data in the two systems, making comparison meaningless.
- Signing off with unexplained variances to hold a date.
- Not testing terminations and back pay.
What should a complete variance log explain?#
Give each variance an employee or transaction reference, pay period, component, expected result, actual result and difference. Record the instrument or approved rule that establishes the expected result. That makes the log a test record rather than a list of opinions about which system looks right.
Separate a wrong input from a wrong rule. If the hours differ between systems, reconcile the inputs before comparing interpretation. If both inputs match but the pay differs, test the clause, effective date, rounding and interactions. Keep evidence where the old system was wrong as well as where the new configuration needs correction.
Retest the affected population after a rule change. A fix for one shift pattern can alter other penalties or allowances. Repeat the original failing case, its boundary cases and the representative regression set. Record the version that passed so a later change doesn't rely on an obsolete screenshot.
Close a variance only when the owner accepts the explanation and the resulting action. An explained difference can still require historical remediation, an employee communication or a reporting correction. Track those actions separately from the go-live decision, with clear owners and completion evidence.
Decision and evidence checklist#
| Situation | Decision to make | Evidence to retain |
|---|---|---|
| A comparison is designed | Use equivalent inputs and include boundary cases | Retain scenario and source versions |
| Results differ | Test both systems against the correct entitlement | Classify old/new error, data, design or unexplained |
| Sign-off is requested | Resolve unexplained differences and verify outputs | Keep owner approvals and retest evidence |
Name an owner for each unresolved item, agree the next action and keep the version of the evidence used for the decision. Close the item when the underlying work is complete, rather than when a message has been sent. Use the record to explain the decision to the employee, the next team or an authorised reviewer.
Our view#
We think parallel runs are the single most important test in a payroll implementation and the first thing cut when a date is at risk. An extra parallel costs days. A bad first live pay costs trust, back pay and sometimes a remediation program.
We'd also prepare clients for a finding many don't expect: parallel runs regularly show the old system was wrong. Have a plan, including legal advice, for what you'll do when that happens.
Worked example#
Illustrative example.
Variance log from parallel run 1, Entity A (fortnightly, 412 employees)
| # | Employees | Difference | Cause | Classification | Action |
|---|---|---|---|---|---|
| 1 | 412 | ±$0.01 | Rounding at line vs total level | Expected | Document |
| 2 | 18 | −$63.00 each | Broken shift allowance not triggered on split shifts over midnight | New system wrong | Fix rule; re-test |
| 3 | 9 | +$41.20 each | Old system missed casual loading on Saturday overtime | Old system wrong | Confirm with payroll lead; legal advice on back pay |
| 4 | 3 | Varies | Timesheets edited in old system after extract | Data difference | Re-extract; re-run |
| 5 | 1 | +$312.00 | Unknown | Unexplained | Investigate. Blocks sign-off |
Run 2 can't be signed off until rows 2, 4 and 5 are closed.
What HR should monitor#
These measures are worth tracking whatever system you use. Report patterns at team, site and role level, with groups large enough to protect individuals.
| What to track | How to measure it | Look closer when |
|---|---|---|
| Variance log status | Open parallel run variances by classification and entity | Any unexplained variance at the readiness gate |
How EmployeeConnect helps#
Include the step from HR to payroll in your parallel runs. Put a new starter, a pay change, leave and a termination through EmployeeConnect as you'll do it live, then check what payroll received and applied. A clean hand-off is one test result. It isn't sign-off of the pay run.
Frequently asked questions #
How many parallel payroll runs should we do?
At least two per pay frequency and entity, and more until every variance is explained.
What if the parallel run finds the old system was wrong?
Confirm the finding, get advice, and decide whether to remediate past periods.
Can an explained variance still block go-live?
Yes. An explanation identifies the cause; it doesn't complete the correction. Close material variances with the responsible owner, retest the affected cases and record the release decision against the agreed acceptance criteria.