Practical field guide
Organisations go live on a new HRIS safely: readiness criteria, cutover steps, first pay run checks, hypercare and the 90-day review.
The short answer#
Go live only when readiness criteria are met: data reconciled and signed off; parallel runs signed off with no unexplained variances; STP, bank and super files tested; GL reconciled; UAT signed off; integrations, security roles and SSO tested; people trained; support model in place; and a rollback plan agreed. Follow a written cutover sequence (freeze, final old-system pay and super, extract, load, reconcile, switch integrations, open access, confirm flows). Treat the first live pay as special: extra checks, a payslip sample, bank file review, same-day super with daily return monitoring, STP confirmation and an off-cycle process ready. Run hypercare until exit criteria are met, then hold a 90-day review.
Why go-live needs extra care#
Go-live isn't the end of the project. It's the moment the system starts doing real work, with real pay and real people depending on it. The weeks either side of go-live need more care than any other point in the project.
Readiness criteria: the go / no-go decision#
Before the steering committee approves go-live, every criterion should be met, or have an accepted, documented workaround.
Data
- Final trial load completed and reconciled
- Leave, YTD, LSL and super balances signed off by payroll and finance
- Bank and super fund details validated
Payroll
- Parallel runs signed off for every entity and pay frequency
- No unexplained variances
- STP connection tested
- Bank file and super file tested with providers
- GL journal reconciled
Configuration and integrations
- User acceptance testing signed off
- All integrations tested end to end
- Security roles tested with real users
- Single sign-on working
People
- HR and payroll trained and confident
- Manager and employee training delivered
- Quick reference guides published
- Support model in place, with names and hours
Contingency
- Rollback plan agreed
- Old system available in read-only (or ready to run if needed)
- Manual payment process ready for urgent cases
Cutover steps#
A typical sequence:
- Freeze changes in the old system from an agreed time
- Final pay run in the old system; send super; confirm
- Extract final data
- Load into the new system
- Reconcile counts and balances against the final extract
- Switch integrations to the new system
- Open access for HR and payroll first, then managers and employees
- Confirm first timesheets and leave requests flowing correctly
Write every step down with an owner and a time. Run through it in the dress rehearsal.
The first live pay run#
Treat the first live pay as a special event:
- Extra checks before finalising: compare totals to the last parallel and last old-system pay; review every exception
- Review a sample of payslips across awards and employee types
- Confirm the bank file before release
- Send super same day and watch returned contributions daily for the next 7 business days. See our Payday Super guide
- Confirm STP lodgement was accepted
- Have a plan for urgent corrections: who can approve an off-cycle payment, and how fast
Hypercare: the first weeks#
Hypercare is a period of intensive support after go-live, usually covering the first few pay cycles.
- Daily check-in between your project lead and the vendor team
- Issue log with priority, owner and status
- Fast response for anything affecting pay
- Visible support for managers and employees
- Communication about known issues and fixes
Exit hypercare based on criteria, not a date: pay runs completing without critical issues, issue log under control, support volumes back to normal.
The 90-day review#
At around 90 days, hold a post-implementation review:
- Did we get what we set out to get? Compare against the business case benefits
- What's working, what isn't?
- Adoption measures by team and site. See our change management guide
- Open issues and enhancements for the next phase
- Lessons for the next phase of modules
Share the results with the steering committee and the executive sponsor. Then close the project formally and hand over to business-as-usual ownership.
Where does a contingency stop being a rollback?#
Identify the last reversible step in the cutover plan. Before payments and reports leave the controlled environment, restoring data and configuration can be a practical fallback. After a bank payment, statutory report or super contribution is transmitted, the response needs an authorised correction or recovery process. A restored backup can't unsend the original transaction.
Keep payment continuity separate from system recovery. Name the person who can authorise a contingency pay route, the checks that prevent duplicates and the method for reconciling transactions entered while the main system is unavailable. Rehearse those steps with payroll, finance, IT and the provider before relying on them.
Close the incident by reconciling the employee-level results, connected outputs and outstanding obligations. Record what was corrected and what still needs follow-up. A system returning online is a technical milestone; correct pay and reporting complete the business recovery.
Decision and evidence checklist#
| Situation | Decision to make | Evidence to retain |
|---|---|---|
| Go-live is proposed | Verify data, pay, integration, access and support evidence | Record decision authority and residual risks |
| Cutover starts | Follow the rehearsed sequence and stop conditions | Keep timestamps and reconciliation evidence |
| Hypercare exit is proposed | Test stable operations and ownership against exit criteria | Retain unresolved issues and acceptance |
Name an owner for each unresolved item, agree the next action and keep the version of the evidence used for the decision. Close the item when the underlying work is complete, rather than when a message has been sent. Use the record to explain the decision to the employee, the next team or an authorised reviewer.
Our view#
We think go-live is the riskiest moment of the project, not the end of it. The weeks either side deserve more care than any other point.
We'd also exit hypercare on criteria, not a calendar date. Two clean pay cycles and a controlled issue log is a better sign than "it's been four weeks".
Worked example#
Illustrative example.
First live pay checks (illustrative, fortnightly, 1,240 employees)
| Check | Last parallel | First live | Difference | Explained? |
|---|---|---|---|---|
| Gross | $3,412,880 | $3,421,305 | +$8,425 | Yes: 6 new starters, 2 terminations |
| Tax | $701,214 | $703,060 | +$1,846 | Yes: same |
| Super (SG) | $409,546 | $410,557 | +$1,011 | Yes: same |
| Net | $2,520,180 | $2,526,640 | +$6,460 | Yes |
| Exceptions | 14 | 21 | +7 | 5 new starters missing fund details, 2 timesheet edits |
The five missing fund details are the priority: under Payday Super, they'll be returned contributions within days unless fixed now.
What HR should monitor#
These measures are worth tracking whatever system you use. Report patterns at team, site and role level, with groups large enough to protect individuals.
| What to track | How to measure it | Look closer when |
|---|---|---|
| Hypercare health | Exceptions, open issues and support requests per pay cycle after go-live, against the parallel baseline | Not trending down by cycle 3 |
How EmployeeConnect helps#
During hypercare, use the real work records in EmployeeConnect, like onboarding progress, review tasks and integration results, to tell the difference between a task waiting on a person and a record that failed to process. Keep those results separate from the go-live decision, and record what was checked and who accepted it.
Frequently asked questions #
What is hypercare?
A period of intensive support after go-live, usually covering the first few pay cycles.
What should we do if the first live pay has errors?
Have an off-cycle payment process ready, fix the root cause, and communicate quickly with affected employees.
Can a backup reverse a payment already sent?
No. Identify the last reversible cutover step. A transmitted payment or statutory report needs an authorised correction or recovery process, with reconciliation to prevent duplicates.