Practical field guide
A practical checklist for your first live pay run.
Start here#
Go live when you can show that people will be paid correctly, payments and reports will work, and the team knows what to do if something fails. A launch date or a matching payroll total is not enough.
Use this guide with your payroll lead, finance lead and the person approving the launch. Work through five steps:
- Check every employee's pay.
- Check payments, reporting and super.
- Make a clear go/no-go decision.
- Plan the first pay and a backup.
- Check the first pay, then follow up.
Keep the reports and test results behind each answer. If you cannot show that an important check has passed, treat it as unfinished—not as a yes.
The Cedar Services example below is fictional. Use it to understand the checks, then apply them to your own payroll.
1. Check every employee's pay#
Run the old and new payroll using the same employees, time records and pay period. This is a parallel run: a comparison before the new system makes a live payment.
Ask your payroll lead to confirm:
- People and balances: everyone in scope is included; leave balances and year-to-date amounts match the agreed source.
- Each person's pay: compare gross pay, tax, deductions, net pay and super—not just the overall total.
- Different pay situations: test the rules you actually use, including allowances, overtime, leave, starters and leavers.
- Imports: a repeated time-file upload must not pay people twice. Also test what happens when an approved record changes.
List every difference, who will investigate it, what must change and how the fix will be checked. Compare pay against the correct entitlement, not just the old system: both systems can make the same mistake.
Example: P101 is $125 below expected gross pay and P102 is $125 above. The total still matches, but both employees' results are wrong.
Agree your checking rules before testing. Every unexplained gross or net pay difference needs investigation. Any accepted rounding difference needs a known, documented rule. Check leave and year-to-date differences too.
After a correction, rerun the affected checks. Keep the input and configuration versions with the results, so everyone knows exactly what passed.
Optional: open the pay-difference log and download a spreadsheet
Payroll variance register
A zero net total does not clear offsetting employee-level errors. Explained does not mean acceptable; retain owner, closure evidence and affected-population work.
| ID | Finding | Classification | Required action | Closure evidence | Opened at | Owner | Closed at | Closure evidence ref | Action |
|---|---|---|---|---|---|---|---|---|---|
Add a variance
2. Check payments, reporting and super#
A correct calculation is only part of a working payroll. Ask the people responsible for each output to check a test produced by the version you intend to launch.
| Check | What you need to confirm |
|---|---|
| Payslips | The employee details, pay components and balances are correct. |
| Bank file | The right people receive the right amounts; the file reconciles to the approved pay run. |
| Single Touch Payroll (STP) | Employee amounts, reporting categories and year-to-date values reconcile to payroll. |
| Super | Earnings are mapped correctly, contributions can reach funds on time, and someone handles rejected or returned payments. |
| Finance | Pay components reach the correct accounts and the general ledger export reconciles to payroll. |
Agree the STP changeover before launch
If you change software or employee payroll IDs during the financial year, agree the approach with your provider and tax adviser. Decide how year-to-date amounts will be handled, what the ATO must be told, and when any old-system finalisation happens. Otherwise, employees may see duplicate income statements.
Reconcile year-to-date amounts by employee and STP category, not just as a grand total. Changing on 1 July can simplify year-to-date handling, but does not remove the need for reporting tests.
Have super working from the first live pay
Under Payday Super, contributions generally need to reach the employee's fund within seven business days after payday. Confirm the applicable rules, exceptions and holiday calendar with current ATO guidance and your adviser. Do not assume employees transferred between payroll systems qualify for a new-employee extension.
Check the qualifying-earnings mapping used for super and STP reporting. Confirm your contribution provider, processing time and rejection process; do not rely on the former Small Business Superannuation Clearing House.
Keep required time and pay records accessible after the changeover. Correcting the new system does not settle a possible historical underpayment: give that assessment a separate owner.
3. Make a clear go/no-go decision#
Hold a short decision meeting with the payroll lead, finance lead and accountable sponsor. Review the checks and open issues—not a percentage-complete score.
Go ahead only when:
- the employees, pay rules and outputs in scope have been tested;
- unexplained differences and errors affecting the live pay have been resolved and retested;
- payroll and finance accept the results, and the normal authorised approvers can release the pay;
- the team has a workable backup and named support contacts.
Postpone if a problem could cause an incorrect payment, duplicate payment, reporting failure or missed obligation and you cannot show it is controlled. Write down what must be fixed and when you will review the decision.
Example: why Cedar Services postponed
Cedar planned to move 412 employees across two entities. Two parallel runs had finished, but:
- two employees still had the offsetting $125 differences;
- replaying a time import created twelve duplicate transactions;
- the finance export had not been reconciled;
- an allowance was missing in both systems, and changed timesheets meant some comparisons used different inputs.
The sponsor postponed the move and kept the established payroll process for the next cycle. The team had to fix and retest these items, with a separate owner assessing any historical allowance impact.
That is a useful no-go decision: keep people paid, name the remaining work, and set the conditions for another decision.
The sponsor owns the launch decision. Payroll and finance accept the results in their areas. The normal payment approvers still authorise the actual pay run. A vendor's statement does not replace these responsibilities.
Optional: open the detailed readiness checklist and export your record
Payroll go-live readiness board
Evidence status is recorded by area and version. A completed area does not offset a gap elsewhere; blockers remain explicit and no readiness percentage is shown.
3 blocker/incomplete areas currently recorded. This is not an automated go/no-go decision.
| Readiness area | Evidence available | Finding | Status | Version | Owner |
|---|---|---|---|---|---|
| Employee population | |||||
| Leave balances | |||||
| Year-to-date values | |||||
| Time import | |||||
| Gross-to-net comparison | |||||
| Payslips | |||||
| Bank-file preparation | |||||
| STP pay event | |||||
| Super contributions | |||||
| Finance export | |||||
| Access and approval | |||||
| Contingency |
Go criteria and tolerance record
| Criterion | Required state |
|---|---|
| Unexplained employee-level variances | None |
| Explained variances that remain incorrect | None, or approved correction before release |
| Blockers in variance register | All closed with evidence |
| Outputs from go-live configuration | Payslip, bank file, STP, super and GL reconciled |
| YTD and leave balances | Reconciled by employee |
| Operators and approvers | Trained; access tested |
| Contingency | Owned; external-release boundary identified |
| Change freeze | From final extract to first-pay close |
Record specific tolerances, date, owner and evidence with this scope before release.
Completed synthetic no-go decision
Continue existing payroll process for next cycle. Corrected independently checked results and end-to-end retest evidence.
Blocking items: V-01, V-02, V-04. This is source example data, not a live decision.
4. Plan the first pay and a backup#
Give every action an owner and a date. Work backwards from payday, leaving time to investigate a failed check.
- Before the final load: tell employees what will change, restrict unapproved configuration changes, and agree the final data cut-off.
- After loading: account for accepted and rejected records. Reconcile people, leave, year-to-date amounts and time inputs.
- Before release: check the actual pay run and its payslips, bank file, STP, super and finance outputs. Obtain the required approvals.
- On payday: check bank acknowledgements, STP receipts and failed or rejected outputs. Assign every exception.
- After payday: confirm super reaches funds within the applicable deadline, reconcile the outputs and record outstanding actions.
Use dates that fit your organisation and providers. The optional workbook contains an illustrative schedule, not an automatic deadline calculator.
Know when you can no longer simply start again
Before a file is released, you may be able to correct it and rerun the calculation. Once a bank payment, STP report or super contribution has been sent, restoring the payroll database does not undo it. A posted finance journal also needs finance's correction process.
For each output, name who checks submission status, contacts the provider and authorises a correction. Reissue incorrect payslips through the controlled process.
Agree how you will continue paying people if launch is postponed. Do not run both old and new payment processes “just in case”—you could pay twice. Use one controlled payment route.
Keep bank details, passwords and sensitive employee records in approved systems, not in a project checklist.
5. Check the first pay, then follow up#
Check what actually happened, even if every test passed. Confirm the right people were paid, investigate rejected outputs and reconcile the live results.
Arrange extra support for the first few pay cycles. Give employees a clear contact, keep an enquiry log and have an authorised way to correct an underpayment promptly. Name the payroll, finance, integration and vendor contacts who can resolve problems.
Agree when extra support can end—for example, after two consecutive cycles without critical exceptions and with enquiries back to normal. That is an example to adapt, not a legal minimum.
Book three follow-up reviews:
- 30 days: were people paid correctly, did super arrive on time, and can support resolve queries?
- 60 days: are temporary workarounds being removed, responsibilities handed over and old records still accessible?
- 90 days: are the expected improvements happening, and are historical issues progressing with their owners?
Track corrections, employee enquiries, late super, STP exceptions, time to approve a run and manual workarounds. Look at the causes and payroll volume, not just a rising or falling count.
Copy this decision note#
Use this short note in your launch meeting. Link to the supporting reports instead of copying sensitive data into it.
| Record | Fill in |
|---|---|
| What are we launching? | Entities, employees, pay cycle, systems and interfaces included. |
| What passed? | Links to employee-level comparisons, balance checks and output reconciliations; record the tested versions. |
| What is still open? | Each issue, who is affected, its owner and the evidence needed to close it. |
| What is the decision? | Go or postpone, with reasons and any conditions. |
| Who accepts it? | Sponsor, payroll lead and finance lead, with the decision date. |
| What happens next? | First live payday, release approvals, action owners and dates. |
| What is the backup? | How people will be paid if the move cannot proceed, and who can activate that plan. |
| Who supports the first pay? | Named contacts, correction process and the first-pay review owner. |
| When will we review it? | Support exit criteria and 30-, 60- and 90-day review dates. |
You do not need to fill in every workbook on this page to understand the decision. Use the optional tools when you need a more detailed issue log, readiness record or first-pay plan. They include fictional completed examples; replace these with your own checked results.
Spreadsheet downloads are labelled CSV. The JSON downloads are structured records for teams that need them. Download anything you need to keep before leaving the page; entries are not saved on a server.
Optional: open the detailed plan and download blank or completed templates
Payroll cutover runbook
Static T-minus workbook based on an illustrative fortnightly cycle. Dates are intentionally not computed; adapt timing to your business-day calendar and confirm rules with providers and official guidance.
| When | Checkpoint / action | Owner | Evidence before proceeding | Record status | Evidence reference | Recorded date |
|---|---|---|---|---|---|---|
| T−20 business days | Gate Confirm scope, outstanding items and change controls | Approved gate record | ||||
| T−15 business days | Communications Notify employees of payslip and access changes | Communication issued | ||||
| T−10 business days | Change freeze No configuration changes without sponsor approval | Freeze notice | ||||
| T−8 business days | Data cut-off Produce versioned employee, balance, YTD and time extracts | Population and control totals | ||||
| T−7 business days | Final load Load data; reconcile rejects, changes and totals | Accepted/rejected record reconciliation | ||||
| T−6 business days | YTD and balances Reconcile YTD by STP category and leave by employee | Signed reconciliation | ||||
| T−5 business days | Calculation Run payroll and investigate exceptions | Employee-level and aggregate checks | ||||
| T−4 business days | Output preparation Produce payslips, bank file, STP, super and finance outputs | Component and population reconciliation | ||||
| T−3 business days | Authorisation Review the actual proposed live run | Run-specific approval | ||||
| T−2 business days | Release Submit only authorised outputs through controlled channels | Submission references and status | ||||
| T (payday) | Confirmation Check bank acknowledgements, STP receipt and failures | Exception list and reconciliation | ||||
| T+1 to T+7 business days | Super confirmation window Confirm contributions received and allocated; resolve returns | Fund confirmations; return log | ||||
| T+3 business days | Close Resolve or assign remaining items and preserve evidence | Closed run record and owned follow-ups |
Outputs and reversibility
| Output | Reversible until | After that point |
|---|---|---|
| Payslips | Published to employees | Issue corrected payslips |
| Bank file | Submitted to bank | Contact bank; recover or adjust through authorised process |
| STP pay event | Lodged | Correct through later pay event/update as appropriate |
| Super contribution | Sent to clearing service or fund | Manage through fund/provider; watch for duplicates |
| GL journal | Posted | Reverse through finance's normal process |
Tolerance record
| Measure | Tolerance | Reason / exception | Owner | Evidence reference |
|---|---|---|---|---|
| Employee-level gross pay | ||||
| Employee-level net pay | ||||
| Rounding | ||||
| Aggregate totals | ||||
| Leave balances | ||||
| YTD by STP category |
Hypercare record
Follow-up reviews
| Review point | Questions | Date entered | Owner | Evidence | Decision |
|---|---|---|---|---|---|
| 30 days | Which live exceptions differed from tests?; Were people paid and outputs reconciled?; Did contributions arrive within applicable timeframe?; Can support resolve enquiries? | ||||
| 60 days | Are temporary workarounds becoming permanent?; Have operational owners accepted responsibilities?; Are old-system records accessible? | ||||
| 90 days | Are intended improvements measurable?; Which controls need strengthening?; Is historical assessment progressing? |
Decision / readiness record fields
T-minus rows and static example are adapted from the source. No real employee data, server storage, CRM or API calls. Exports include version and assumptions; use authorised evidence locations for sensitive records.
Common questions#
Are two parallel runs enough?
Not on their own. What matters is whether the tests covered your payroll and whether errors were corrected and retested. Two runs with the same unresolved problem do not prove readiness.
Can we accept a difference we understand?
Only if it is a correct, justified and approved difference. Knowing why someone is underpaid does not make the underpayment acceptable.
Can we move one entity first?
Possibly. Check shared integrations, employees working across entities, reporting, super and support capacity. The smaller launch needs its own checks and approval.
Is 1 July the best launch date?
It can simplify year-to-date transfer, but payroll teams also face annual changes and year-end work then. Choose a date your team can support; it is not a substitute for testing.
What if the launch date cannot move?
Escalate early and use a controlled plan to meet payroll obligations. A fixed deadline does not make an unchecked pay run correct.
Who makes the final decision?
The accountable sponsor, with payroll and finance accepting their results. Normal delegations still apply to releasing the actual pay.
Need help with an open issue?#
Bring a short list: what failed, who is affected, what you expected and what has already been tested. That makes a discussion with your payroll provider or implementation team more useful.
Talk to EmployeeConnect about your payroll implementation.
For more detail, use the parallel-run guide and award setup guide.
Sources checked during drafting#
- ATO, Changing your payroll solution or employees' Payroll IDs.
- ATO, How Payday Super works and Managing the changeover to Payday Super.
- Fair Work Ombudsman, Record-keeping and Criminalising wage underpayments.
Changelog #
- : Initial approved edition prepared for publication.